Monday 14 January 2019

Factory #183 Experiments

"July 2nd, 1940

To ABTU 8th Department Chief, Military Engineer 1st Class, comrade Afonin

Report on experimental work performed at factory #183 in June 1940

The following experimental work was performed in June of 1940.
  1. Trials of two A-7M vehicles ## 0314-2 and 903-03 with substitutes. A number of parts on these vehicles use iron instead of bronze or aluminium. A number of parts were also made from cheaper steels rather than highly hardened steel. Trials were completed, micro-measurements are being performed.
  2. Reliability trials of A-7M #327-45 have finished. The vehicle completed 3000 km trials. The report is being completed.
  3. Two engines from factory #75 are undergoing 150 hour trials. The engines were installed on A-7M ## 0890-3 and 442-55. The first engine worked for 70 hours and was removed due to significant leaking of gases between the cylinder block and head. The second worked for 125 hours, after which gases started penetrating into the water and throwing the cooling system water out through the reductor. A chronic defect of this diesel engine, breakdown of the automatic timing device, was also observed.
  4. Trials of a T-34 #0311-11-3 with track links cast from Hadfield steel, mechanical controls instead of pneumatic servos, and a reinforced cooling fan are being performed.
  5. The A-5 tank with the V-3 engine is being repaired. Work is going slowly due to plant #500 being loaded with production of the T-34 tank. The repairs are also slowed down due to the fact that blueprints and detailed descriptions are absent. The repairs are planned to be completed by July 10th.
  6. Voroshilovets tractor #68 warranty trials continue. 700 km remain.
  7. Tractor #7 with a V-3 diesel engine is being trialled. Trials will be complete in early July.
  8. Completion of the agreement between factory #183 and the Chemical Directorate is delayed. Assembly blueprints are complete, all that remains is for the Chemical Directorate to give final consultations and send the technical project to be approved. All other blueprints can be readied by early August.
  9. Development of a new project for a tractor on the T-34 chassis is complete. Assembly blueprints are being copied and detailed blueprints are being made. The development of detailed blueprints can be finished by August 10-15th. Delays in producing the blueprints can be explained by a shortage of copiers.
  10. Production of pneumatic components for the Voroshilovets tractor is in progress. Two prototypes may be assembled in July.
Senior Military Representation, Military Engineer 2nd Class, Kozyrev
Military Representation, Military Engineer 3nd Class, Baikov"

No comments:

Post a Comment