Order #40
Code 73-P
Item
|
Calculations
|
Total
|
Direct spending
|
||
Main materials
|
Steel, other materials
|
1,400
|
Purchased parts
|
3 barrels, 500 rub. Each
|
1,500
|
Salaries
|
||
Machinists
|
1650 man-hours*3.01
|
4,970
|
Millers
|
650 man-hours*3.10
|
2,020
|
Planers
|
350 man-hours*2.50
|
870
|
Tracers
|
50 man-hours*3.00
|
150
|
Metalworkers
|
1400 man-hours*3.15
|
4,410
|
Fitters
|
500 man-hours*3.57
|
1,790
|
Auxiliary plant workers
|
100 man-hours*3.30
|
330
|
Total
|
14,540
|
|
Engineering-Technician works
|
||
Lead Designer
|
5.5 man-months*2000
|
11,000
|
Designers
|
3 man-months*1000
|
3,000
|
Engineer-Technologist
|
1.5 man-months*1200
|
1,800
|
Senior Engineers
|
2 man-months*1200
|
2,400
|
Engineers
|
0.5 man-months*1000
|
500
|
Total
|
18,700
|
|
Design Department Workers
|
||
Drafter
|
3 man-months*400
|
1,200
|
Tracer
|
2 man-months*300
|
600
|
Total salaries
|
35,040
|
|
Total direct spending
|
37,940
|
|
Additional spending
|
||
Work at the plants
|
35,040
|
|
General factory spending
|
17,520
|
|
Special spending
|
||
Instruments and devices
|
1,000
|
|
Proving grounds and transport costs
|
600
|
|
Ammunition for preliminary trials
|
1000 * 25 rubles
|
25,000
|
Trips to trials
|
4,000
|
|
External services
|
260
|
|
Total
|
30,860
|
|
Total additional spending
|
83,420
|
|
Total factory spending
|
121,360
|
|
3% interest
|
3,640
|
|
Total cost
|
125,000
|
Lead designer Rashkov
Chief of the Planning and Production Department, Rodin"