"Order of the People's Commissariat of Defense #80-Mss
Moscow
December 27th, 1941

Referring to the decree of the State Committee of Defense #GKO-1043ss issued on December 19th, 1941, I order to:

1. Establish the following schedule for daily production in January of 1942 of tanks, hulls, and engines between the NKTP factories:
Factory
Item
Total in January 1942
10-day intervals of January 1942
1st
2nd
3rd
Tank production
Kirov factory
KV tank
435
12
14/15
17
Factory #183
T-34 tank
430
10
15
18
STZ
T-34 tank
308
9
10
12
Factory #112
T-34 tank
250
7
8
10
Factory #174
T-50 tank
210
5
7
9
Factory #37
T-60 tank
250
6
8
11
Factory #38
T-60 tank
200
4
6
10
Factory #264
T-60 tank
240
6
8
10
Engine production
Kirov factory
V-2 engine
645
16
22
26
STZ
V-2 engine
330
9
12
12
Factory #76
V-2 engine
360
10
12
14
Hull production
Izhora factory
KV hull
380
10
13
15
Factory #200
KV hull
130
3
4
6
Factory #264
T-34 hull
350
10
12
13
Factory #37
T-60 hull
260
6
9
11
Factory #38
T-60 hull
220
5
7
10
Kulebaki factory #178
T-60 hull
100
2
3
5
Murom factory #176
T-60 hull
410
13
14
14
Vyksa factory #177
T-60 hull
260
8
9
10
Factory #183
T-34 hull
450
10
16
18/19
Factory #112
T-34 hull
275
7
9
11
Saratov factory #180
T-50 hull
240
6
8
10
2. Consider that the schedule for January 1942 includes one holiday.
3. All directors of tank, hull, and engine factories must send me encrypted messages regarding the production of tanks, hulls, and engines in January of 1942 daily.

People's Commissar of Tank Production of the USSR, Malyshev"