"Order of the People's Commissariat of Defense #80-Mss
Moscow
December 27th, 1941
Referring to the decree of the State Committee of Defense #GKO-1043ss issued on December 19th, 1941, I order to:
1. Establish the following schedule for daily production in January of 1942 of tanks, hulls, and engines between the NKTP factories:
Factory
|
Item
|
Total in January 1942
|
10-day intervals of January 1942
|
||
1st
|
2nd
|
3rd
|
|||
Tank production
|
|||||
Kirov factory
|
KV tank
|
435
|
12
|
14/15
|
17
|
Factory #183
|
T-34 tank
|
430
|
10
|
15
|
18
|
STZ
|
T-34 tank
|
308
|
9
|
10
|
12
|
Factory #112
|
T-34 tank
|
250
|
7
|
8
|
10
|
Factory #174
|
T-50 tank
|
210
|
5
|
7
|
9
|
Factory #37
|
T-60 tank
|
250
|
6
|
8
|
11
|
Factory #38
|
T-60 tank
|
200
|
4
|
6
|
10
|
Factory #264
|
T-60 tank
|
240
|
6
|
8
|
10
|
Engine production
|
|||||
Kirov factory
|
V-2 engine
|
645
|
16
|
22
|
26
|
STZ
|
V-2 engine
|
330
|
9
|
12
|
12
|
Factory #76
|
V-2 engine
|
360
|
10
|
12
|
14
|
Hull production
|
|||||
Izhora factory
|
KV hull
|
380
|
10
|
13
|
15
|
Factory #200
|
KV hull
|
130
|
3
|
4
|
6
|
Factory #264
|
T-34 hull
|
350
|
10
|
12
|
13
|
Factory #37
|
T-60 hull
|
260
|
6
|
9
|
11
|
Factory #38
|
T-60 hull
|
220
|
5
|
7
|
10
|
Kulebaki factory #178
|
T-60 hull
|
100
|
2
|
3
|
5
|
Murom factory #176
|
T-60 hull
|
410
|
13
|
14
|
14
|
Vyksa factory #177
|
T-60 hull
|
260
|
8
|
9
|
10
|
Factory #183
|
T-34 hull
|
450
|
10
|
16
|
18/19
|
Factory #112
|
T-34 hull
|
275
|
7
|
9
|
11
|
Saratov factory #180
|
T-50 hull
|
240
|
6
|
8
|
10
|
2. Consider that the schedule for January 1942 includes one holiday.
3. All directors of tank, hull, and engine factories must send me encrypted messages regarding the production of tanks, hulls, and engines in January of 1942 daily.
People's Commissar of Tank Production of the USSR, Malyshev"